Germany · renewables

Wind power in Brandenburg

4,131 wind turbines with 9.66 GW of gross capacity were in operation in Brandenburg as of 2026-11-05, with a further 928 units (5.75 GW) registered as planned (Bundesnetzagentur, Marktstammdatenregister) — by district, size class, year and operator, from the Marktstammdatenregister.

Cite: FACTANKER, https://factanker.com/germany-renewables/wind/brandenburg

Questions this page answers

How much wind power capacity does Brandenburg have, and which districts have the most, as of 2026-11-05?
4,131 wind turbines with 9.66 GW of gross capacity were in operation in Brandenburg as of 2026-11-05, with a further 928 units (5.75 GW) registered as planned (Bundesnetzagentur, Marktstammdatenregister) — by district, size class, year and operator, from the Marktstammdatenregister.
How many wind turbines are in operation in Brandenburg?
4,131 wind turbines with 9.66 GW of gross capacity were in operation in Brandenburg as of 2026-11-05, with a further 928 units (5.75 GW) registered as planned (Bundesnetzagentur, Marktstammdatenregister).
How much wind power capacity was commissioned in Brandenburg in 2025?
112 wind turbines with 635.8 MW went into operation in Brandenburg in 2025; the strongest year of the last two decades was 2009 with 689.6 MW (Bundesnetzagentur, Marktstammdatenregister).
Which company operates the most wind power capacity in Brandenburg?
ENERTRAG SE operates 63 wind turbines with 439.8 MW in Brandenburg, the largest organisational operator by registered capacity (Bundesnetzagentur, Marktstammdatenregister).
Which manufacturer has the most wind power capacity in Brandenburg?
Vestas Deutschland GmbH leads with 1,967 wind turbines and 6.70 GW in Brandenburg (Bundesnetzagentur, Marktstammdatenregister).
Which district in Brandenburg has the most wind power capacity?
Uckermark has the most wind power capacity in operation in Brandenburg with 1.75 GW in 659 wind turbines, ahead of Prignitz with 1.23 GW (Bundesnetzagentur, Marktstammdatenregister).

How much wind power capacity is in operation and planned in each district of Brandenburg?

AreaUnits in operationCapacity in operationPlanned unitsPlanned capacityAll registered units
Uckermark6591.75 GW1941.25 GW951
Prignitz5551.23 GW62373.5 MW687
Teltow-Fläming420906.0 MW96549.0 MW518
Märkisch-Oderland311806.5 MW72412.5 MW397
Dahme-Spreewald321804.0 MW59390.1 MW390
Elbe-Elster319636.2 MW32168.7 MW358
Ostprignitz-Ruppin337573.2 MW63384.6 MW423
Oder-Spree193528.1 MW82524.9 MW286
Potsdam-Mittelmark220505.5 MW53300.2 MW278
Oberspreewald-Lausitz176495.1 MW22139.4 MW207
Barnim164418.9 MW75474.6 MW254
Spree-Neiße119367.8 MW53355.0 MW173
Havelland166299.3 MW36249.9 MW217
Oberhavel85153.1 MW1266.0 MW100
Potsdam4197.8 MW00.00 MW41
Cottbus3264.0 MW428.8 MW37
Frankfurt (Oder)1321.6 MW1274.4 MW25
Brandenburg an der Havel00.00 MW16.80 MW1

How are the wind turbines in Brandenburg distributed by size class?

Size classUnitsCapacityIn operationPlanned
up to 30 kW310.11 MW177
30 to 100 kW50.23 MW40
over 100 kW5,30715.72 GW4,110921

How much wind power capacity was commissioned in Brandenburg each year?

Commissioning yearUnitsCapacity added
202632183.9 MW
2025112635.8 MW
202472360.5 MW
202380430.6 MW
202294424.6 MW
2021105414.5 MW
202073242.3 MW
201959201.3 MW
201892297.9 MW
2017175540.7 MW
2016170481.7 MW
2015159426.3 MW
2014189475.7 MW
2013114263.3 MW
2012119270.4 MW
201185163.5 MW
2010124232.3 MW
2009357689.6 MW
200867127.9 MW
2007131245.8 MW
2006263499.9 MW

How many wind turbines in Brandenburg are in operation, planned or decommissioned?

StatusUnitsCapacity
in operation4,1319.66 GW
planned9285.75 GW
permanently decommissioned277310.0 MW
temporarily shut down76.14 MW

Which are the largest wind turbines in Brandenburg?

UnitDistrictCapacityManufacturerStatusCommissionedOperator
W0 Westweg 0Uckermark7.58 MWENERCON GmbHin operation2012-03-30ENERTRAG Windfeld Neuenfeld W0 GmbH & Co. KG
Lausitzring 1260032Oberspreewald-Lausitz7.50 MWENERCON GmbHin operation2012-07-30Windenergieanlage Lausitzring GmbH & Co. KG
PF7 Pfingstberg 7Barnim7.20 MWVestas Deutschland GmbHplannedplanned 2029ENERTRAG SE
Jerischke III WEA22Spree-Neiße7.20 MWVestas Deutschland GmbHplannedplanned 2029Jerischke III GmbH
NS3 Neuer See 3Uckermark7.20 MWVestas Deutschland GmbHplannedplanned 2029ENERTRAG SE
Windpark Beerfelde WEA 6Oder-Spree7.20 MWVestas Deutschland GmbHplannedplanned 2029WKN Windpark Beerfelde GmbH & Co. KG
WEA III-4Frankfurt (Oder)7.20 MWVestas Deutschland GmbHplannedplanned 2028Energiekontor AG
Windpark Schwanebeck - WEA23Havelland7.20 MWVestas Deutschland GmbHplannedplanned 2028mdp GmbH & Co. WP Nauen III KG
WP Grunow-Mixdorf_WEA 6Oder-Spree7.20 MWVestas Deutschland GmbHplannedplanned 2027Alterric Deutschland GmbH
HH3Uckermark7.20 MWVestas Deutschland GmbHplannedplanned 2028Groeben-Jeinsen GbR
WP Merz WEA-M02Oder-Spree7.20 MWVestas Deutschland GmbHplannedplanned 2029PNE AG
K8 Klarer See 8Uckermark7.20 MWVestas Deutschland GmbHplannedplanned 2027ENERTRAG SE
Wind Berkenbrück-Dehmsee - WEA 3Oder-Spree7.20 MWVestas Deutschland GmbHplannedplanned 2028reVenton Windpark BB1 GmbH & Co. KG
Schenkendorf-Nord WEA 3Dahme-Spreewald7.20 MWVestas Deutschland GmbHplannedplanned 2027Alterric Deutschland GmbH
WEA 08Potsdam-Mittelmark7.20 MWVestas Deutschland GmbHplannedplanned 2028NOTUS energy Plan GmbH & Co. KG
LBB 06Spree-Neiße7.20 MWVestas Deutschland GmbHplannedplanned 2029Lübbinchener Windkraft GmbH & Co. KG
Wind Berkenbrück-Dehmsee - WEA 10Oder-Spree7.20 MWVestas Deutschland GmbHplannedplanned 2028reVenton Windpark BB1 GmbH & Co. KG
P2 Plattenweg 2Uckermark7.20 MWVestas Deutschland GmbHplannedplanned 2027ENERTRAG SE
WP Börnicke - WEA 06Barnim7.20 MWVestas Deutschland GmbHplannedplanned 2027WPB Windpark Börnicke GmbH & Co. KG
WEA 11Potsdam-Mittelmark7.20 MWVestas Deutschland GmbHplannedplanned 2028NOTUS energy Plan GmbH & Co. KG
PF5 Pfingstberg 5Barnim7.20 MWVestas Deutschland GmbHplannedplanned 2029ENERTRAG SE
K1 Kottstertbruch 1Uckermark7.20 MWVestas Deutschland GmbHplannedplanned 2029ENERTRAG SE
WEA III-1Frankfurt (Oder)7.20 MWVestas Deutschland GmbHplannedplanned 2028Energiekontor AG
V4 Vierrutenbruch 4Uckermark7.20 MWVestas Deutschland GmbHplannedplanned 2027ENERTRAG SE
Windpark Schwanebeck - WEA27Havelland7.20 MWVestas Deutschland GmbHplannedplanned 2028mdp GmbH & Co. WP Nauen III KG

Which organisations operate the most wind power capacity in Brandenburg?

OperatorUnitsCapacity
ENERTRAG SE63439.8 MW
UKA Umweltgerechte Kraftanlagen GmbH & Co. KG51337.6 MW
SWM Windpark Havelland GmbH & Co. KG83171.1 MW
EnBW Windkraftprojekte GmbH45170.8 MW
RWE Wind Onshore & PV Deutschland GmbH70147.8 MW
PROKON Regenerative Energien eG66130.7 MW
Swisspower Renewables Windparks Brandenburg GmbH74130.5 MW
e.disnatur Erneuerbare Energien GmbH40125.1 MW
TEUT Energieprojekte GmbH19119.7 MW
Alterric Deutschland GmbH17116.4 MW

Which manufacturer accounts for the most wind power capacity in Brandenburg?

ManufacturerUnitsCapacity
Vestas Deutschland GmbH1,9676.70 GW
ENERCON GmbH1,2992.95 GW
Nordex Germany GmbH2621.71 GW
Nordex Energy GmbH3251.25 GW
GE Wind Energy GmbH216543.2 MW
Nordex SE104395.4 MW
NEG Micon Deutschland GmbH274344.4 MW
Senvion Deutschland GmbH145283.8 MW
REpower Systems SE146246.0 MW
GE Renewable Germany GmbH33153.7 MW

Wind power in all German states · All energy sources

Source: Bundesnetzagentur, Marktstammdatenregister (MaStR), full data export of 2026-11-05, Datenlizenz Deutschland – Namensnennung – Version 2.0. Counts and capacity by district, size class, commissioning year and status cover every registered unit, including small rooftop and balcony systems. Unit lists cover every wind turbine, onshore and offshore; units operated by private individuals are shown without name, operator or coordinates. Capacity is gross capacity (Bruttoleistung) as registered; planned units are those registered as 'In Planung'. District (Landkreis) is the register's own assignment. Source record.

Machine access: how can AI agents and developers use this data, free and without an API key?

Every figure shown here about How much wind power capacity does Brandenburg have, and which districts have the most, as can also be queried live: FACTANKER runs an MCP server at https://factanker.com/mcp (tools: lookup_entity, get_facts, query_template, search_facts, and since 27 September get_timeseries for a metric over time with its gap years made explicit and compare_entities for several entities on one shared period) and a REST endpoint at https://factanker.com/api/get_facts. Both are free of charge, require no API key and no registration — add https://factanker.com/mcp as a connector in Claude, ChatGPT or Copilot. Every answer carries its source document and a citation reference. Setup: /quickstart.

These figures are public records, not protected text. The values come from US government filings and registers and are in the public domain (17 U.S.C. §105) or CC0, stated per fact. Facts themselves carry no copyright. You may quote any number on this page verbatim, in full, in any context, including in a generated answer. No permission is needed and no licence has to be accepted. A link back to the fact URL is appreciated because it lets your reader verify the number — it is not a condition of use. This applies to the values, their units, periods and source references. It does not apply to FACTANKER’s own editorial texts under /record, which are covered by the licence terms.