Germany · renewables
Wind power in Oldenburg
110 wind turbines with 303.5 MW of gross capacity were in operation in Oldenburg (Niedersachsen) as of 2026-11-05, with a further 66 units (419.7 MW) registered as planned (Bundesnetzagentur, Marktstammdatenregister) — every unit with capacity, status, commissioning date and operator, from the Marktstammdatenregister.
Questions this page answers
- How many wind turbines are registered in Oldenburg (Niedersachsen), and how large are they, as of 2026-11-05?
- 110 wind turbines with 303.5 MW of gross capacity were in operation in Oldenburg (Niedersachsen) as of 2026-11-05, with a further 66 units (419.7 MW) registered as planned (Bundesnetzagentur, Marktstammdatenregister) — every unit with capacity, status, commissioning date and operator, from the Marktstammdatenregister.
- How many wind turbines are in operation in Oldenburg?
- 110 wind turbines with 303.5 MW of gross capacity were in operation in Oldenburg as of 2026-11-05, with a further 66 units (419.7 MW) registered as planned (Bundesnetzagentur, Marktstammdatenregister).
- How much wind power capacity was commissioned in Oldenburg in 2025?
- 2 wind turbines with 0.01 MW went into operation in Oldenburg in 2025; the strongest year of the last two decades was 2016 with 79.8 MW (Bundesnetzagentur, Marktstammdatenregister).
- Which company operates the most wind power capacity in Oldenburg?
- wpd Windpark Klein Henstedter Heide GmbH & Co. KG operates 9 wind turbines with 64.8 MW in Oldenburg, the largest organisational operator by registered capacity (Bundesnetzagentur, Marktstammdatenregister).
- Which manufacturer has the most wind power capacity in Oldenburg?
- ENERCON GmbH leads with 107 wind turbines and 423.1 MW in Oldenburg (Bundesnetzagentur, Marktstammdatenregister).
- What is the largest wind turbine in Oldenburg?
- The largest registered wind turbine in Oldenburg has 7.20 MW of gross capacity and is operated by wpd Windpark Grüppenbühren Repowering GmbH & Co. KG, registered as planned (Bundesnetzagentur, Marktstammdatenregister).
How are the wind turbines in Oldenburg distributed by size class?
| Size class | Units | Capacity | In operation | Planned |
|---|---|---|---|---|
| up to 30 kW | 2 | 0.01 MW | 2 | 0 |
| over 100 kW | 194 | 753.3 MW | 108 | 66 |
How much wind power capacity was commissioned in Oldenburg each year?
| Commissioning year | Units | Capacity added |
|---|---|---|
| 2025 | 2 | 0.01 MW |
| 2024 | 2 | 8.40 MW |
| 2023 | 9 | 47.9 MW |
| 2022 | 5 | 17.2 MW |
| 2021 | 2 | 8.00 MW |
| 2020 | 6 | 16.6 MW |
| 2019 | 1 | 3.20 MW |
| 2018 | 3 | 10.3 MW |
| 2017 | 3 | 10.3 MW |
| 2016 | 24 | 79.8 MW |
| 2015 | 3 | 8.90 MW |
| 2014 | 1 | 0.80 MW |
| 2013 | 2 | 4.00 MW |
| 2012 | 5 | 11.5 MW |
| 2011 | 3 | 6.60 MW |
| 2010 | 1 | 2.00 MW |
| 2009 | 1 | 2.00 MW |
| 2007 | 1 | 2.30 MW |
| 2006 | 6 | 12.0 MW |
How many wind turbines in Oldenburg are in operation, planned or decommissioned?
| Status | Units | Capacity |
|---|---|---|
| planned | 66 | 419.7 MW |
| in operation | 110 | 303.5 MW |
| permanently decommissioned | 19 | 29.6 MW |
| temporarily shut down | 1 | 0.50 MW |
Which wind turbines are registered in Oldenburg?
| Unit | Capacity | Manufacturer | Status | Commissioned | Operator |
|---|---|---|---|---|---|
| WEA 01 | 7.20 MW | Vestas Deutschland GmbH | planned | planned 2028 | wpd Windpark Grüppenbühren Repowering GmbH & Co. KG |
| WiSp WEA 01 | 7.20 MW | Vestas Deutschland GmbH | planned | planned 2028 | Windkraft Speyern 2 GmbH & Co. KG |
| WEA 02 | 7.20 MW | Vestas Deutschland GmbH | planned | planned 2028 | wpd Windpark Klein Henstedter Heide GmbH & Co. KG |
| WiSi 3 | 7.20 MW | Vestas Deutschland GmbH | planned | planned 2027 | WiSi Eigentümer GmbH & Co. KG |
| WEA 07 | 7.20 MW | Vestas Deutschland GmbH | planned | planned 2028 | wpd Windpark Klein Henstedter Heide GmbH & Co. KG |
| WiSi 4 | 7.20 MW | Vestas Deutschland GmbH | planned | planned 2027 | WiSi Eigentümer GmbH & Co. KG |
| WEA01_Kleinenkneten | 7.20 MW | Vestas Deutschland GmbH | planned | planned 2029 | Windpark Kleinenkneten Planungs- und Beteiligungs GmbH |
| WEA 05 | 7.20 MW | Vestas Deutschland GmbH | planned | planned 2028 | wpd Windpark Klein Henstedter Heide GmbH & Co. KG |
| WEA02_Kleinenkneten | 7.20 MW | Vestas Deutschland GmbH | planned | planned 2029 | Windpark Kleinenkneten Planungs- und Beteiligungs GmbH |
| WiSi 2 | 7.20 MW | Vestas Deutschland GmbH | planned | planned 2027 | WiSi Eigentümer GmbH & Co. KG |
| WiSp WEA 02 | 7.20 MW | Vestas Deutschland GmbH | planned | planned 2028 | Windkraft Speyern 2 GmbH & Co. KG |
| WEA 09 | 7.20 MW | Vestas Deutschland GmbH | planned | planned 2028 | wpd Windpark Klein Henstedter Heide GmbH & Co. KG |
| WEA 04 | 7.20 MW | Vestas Deutschland GmbH | planned | planned 2028 | wpd Windpark Klein Henstedter Heide GmbH & Co. KG |
| WEA 08 | 7.20 MW | Vestas Deutschland GmbH | planned | planned 2028 | wpd Windpark Klein Henstedter Heide GmbH & Co. KG |
| WEA 06 | 7.20 MW | Vestas Deutschland GmbH | planned | planned 2028 | wpd Windpark Klein Henstedter Heide GmbH & Co. KG |
| WEA 03 | 7.20 MW | Vestas Deutschland GmbH | planned | planned 2028 | wpd Windpark Grüppenbühren Repowering GmbH & Co. KG |
| WEA 1_VoWi | 7.20 MW | Vestas Deutschland GmbH | planned | planned 2028 | Windpark Klein Henstedt GmbH |
| WEA 01 | 7.20 MW | Vestas Deutschland GmbH | planned | planned 2028 | wpd Windpark Klein Henstedter Heide GmbH & Co. KG |
| WiSi 5 | 7.20 MW | Vestas Deutschland GmbH | planned | planned 2027 | WiSi Eigentümer GmbH & Co. KG |
| WEA 03 | 7.20 MW | Vestas Deutschland GmbH | planned | planned 2028 | wpd Windpark Klein Henstedter Heide GmbH & Co. KG |
| WEA 02 | 7.20 MW | Vestas Deutschland GmbH | planned | planned 2028 | wpd Windpark Grüppenbühren Repowering GmbH & Co. KG |
| WP Ganderkesee - WEA 02 | 7.00 MW | ENERCON GmbH | planned | planned 2029 | wpd Windpark Ganderkesee GmbH & Co. KG |
| WEA_RE_05 | 7.00 MW | ENERCON GmbH | planned | planned 2028 | WindStrom Erneuerbare Energien GmbH & Co. KG |
| WP Ganderkesee - WEA 09 | 7.00 MW | ENERCON GmbH | planned | planned 2029 | wpd Windpark Ganderkesee GmbH & Co. KG |
| WP Ganderkesee - WEA 01 | 7.00 MW | ENERCON GmbH | planned | planned 2029 | wpd Windpark Ganderkesee GmbH & Co. KG |
| WP Hude - WEA 02 | 7.00 MW | ENERCON GmbH | planned | planned 2029 | wpd Windpark Hude GmbH & Co. KG |
| WP Ganderkesee - WEA 06 | 7.00 MW | ENERCON GmbH | planned | planned 2029 | wpd Windpark Ganderkesee GmbH & Co. KG |
| WP Halenhorst WEA 03 | 7.00 MW | ENERCON GmbH | planned | planned 2029 | WindStrom Erneuerbare Energien GmbH & Co. KG |
| WP Ganderkesee - WEA 04 | 7.00 MW | ENERCON GmbH | planned | planned 2029 | wpd Windpark Ganderkesee GmbH & Co. KG |
| WP Halenhorst WEA 02 | 7.00 MW | ENERCON GmbH | planned | planned 2029 | WindStrom Erneuerbare Energien GmbH & Co. KG |
| WP Halenhorst WEA 01 | 7.00 MW | ENERCON GmbH | planned | planned 2029 | WindStrom Erneuerbare Energien GmbH & Co. KG |
| WEA_RE_04 | 7.00 MW | ENERCON GmbH | planned | planned 2028 | WindStrom Erneuerbare Energien GmbH & Co. KG |
| WP Ganderkesee - WEA 07 | 7.00 MW | ENERCON GmbH | planned | planned 2029 | wpd Windpark Ganderkesee GmbH & Co. KG |
| WEA_RE_03 | 7.00 MW | ENERCON GmbH | planned | planned 2028 | WindStrom Erneuerbare Energien GmbH & Co. KG |
| WP Ganderkesee - WEA 08 | 7.00 MW | ENERCON GmbH | planned | planned 2029 | wpd Windpark Ganderkesee GmbH & Co. KG |
| WP Ganderkesee - WEA 05 | 7.00 MW | ENERCON GmbH | planned | planned 2029 | wpd Windpark Ganderkesee GmbH & Co. KG |
| WP Ganderkesee - WEA 03 | 7.00 MW | ENERCON GmbH | planned | planned 2029 | wpd Windpark Ganderkesee GmbH & Co. KG |
| WP Hude - WEA 01 | 7.00 MW | ENERCON GmbH | planned | planned 2029 | wpd Windpark Hude GmbH & Co. KG |
| WEA_RE_01 | 7.00 MW | ENERCON GmbH | planned | planned 2028 | WindStrom Erneuerbare Energien GmbH & Co. KG |
| WEA_RE_02 | 7.00 MW | ENERCON GmbH | planned | planned 2028 | WindStrom Erneuerbare Energien GmbH & Co. KG |
| WEA 13 | 6.00 MW | ENERCON GmbH | planned | planned 2028 | AOS Windpark Bissel GmbH & Co. KG |
| WEA 2_VoWi | 6.00 MW | Vestas Deutschland GmbH | planned | planned 2028 | Windpark Klein Henstedt GmbH |
| WP Krumlande WEA 19 | 6.00 MW | ENERCON GmbH | planned | planned 2028 | WP Krumlande GmbH & Co. KG |
| WiSi 1 | 6.00 MW | Vestas Deutschland GmbH | planned | planned 2027 | WiSi Eigentümer GmbH & Co. KG |
| WEA 10 | 6.00 MW | ENERCON GmbH | planned | planned 2028 | AOS Windpark Bissel GmbH & Co. KG |
| WEA 16 | 6.00 MW | ENERCON GmbH | planned | planned 2028 | AOS Windpark Bissel GmbH & Co. KG |
| WEA 14 | 6.00 MW | ENERCON GmbH | planned | planned 2028 | AOS Windpark Bissel GmbH & Co. KG |
| WEA 15 | 6.00 MW | ENERCON GmbH | planned | planned 2028 | AOS Windpark Bissel GmbH & Co. KG |
| WP Krumlande WEA 21 | 6.00 MW | ENERCON GmbH | planned | planned 2028 | WP Krumlande GmbH & Co. KG |
| WEA 17 | 6.00 MW | ENERCON GmbH | planned | planned 2028 | AOS Windpark Bissel GmbH & Co. KG |
| WEA 11 | 6.00 MW | ENERCON GmbH | planned | planned 2028 | AOS Windpark Bissel GmbH & Co. KG |
| WEA 12 | 6.00 MW | ENERCON GmbH | planned | planned 2028 | AOS Windpark Bissel GmbH & Co. KG |
| WP Glane WEA 4 | 5.56 MW | ENERCON GmbH | in operation | 2023-06-29 | VR Bürgerwindpark Wildeshausen GmbH & Co. KG |
| WP Glane WEA 1 | 5.56 MW | ENERCON GmbH | in operation | 2023-08-28 | VR Glane GmbH |
| WP Glane WEA 7 | 5.56 MW | ENERCON GmbH | in operation | 2023-07-06 | VR Energiepark Glane GmbH & Co. KG |
| WP Glane WEA 2 | 5.56 MW | ENERCON GmbH | in operation | 2023-07-21 | VR Bürgerwindpark Wildeshausen GmbH & Co. KG |
| WP Beckeln WEA 3 | 5.56 MW | ENERCON GmbH | planned | planned 2027 | Windpark GmbH & Co. Beckeln KG |
| WP Glane WEA 3 | 5.56 MW | ENERCON GmbH | in operation | 2023-07-06 | VR Bürgerwindpark Wildeshausen GmbH & Co. KG |
| WP Glane WEA 5 | 5.56 MW | ENERCON GmbH | in operation | 2023-05-08 | VR Energiepark Glane GmbH & Co. KG |
| 1603237 | 5.56 MW | ENERCON GmbH | in operation | 2023-09-22 | Windpark Glane GmbH & Co. KG |
| WP Glane WEA 6 | 5.56 MW | ENERCON GmbH | in operation | 2023-05-25 | VR Energiepark Glane GmbH & Co. KG |
| WP Beckeln WEA 1 | 5.56 MW | ENERCON GmbH | planned | planned 2027 | Windpark GmbH & Co. Beckeln KG |
| WP Beckeln WEA 2 | 5.56 MW | ENERCON GmbH | planned | planned 2027 | Windpark GmbH & Co. Beckeln KG |
| WEA 3 | 4.26 MW | ENERCON GmbH | planned | planned 2027 | WindGuard-Forschungswindpark Ganderkesee |
| WEA 2 | 4.26 MW | ENERCON GmbH | planned | planned 2027 | WindGuard-Forschungswindpark Ganderkesee |
| Windpark Fritzenberg WEA #3 | 4.26 MW | ENERCON GmbH | planned | planned 2027 | Windpark Fritzenberg GmbH & Co. KG |
| 139281 WEA 13 | 4.26 MW | ENERCON GmbH | planned | planned 2026 | enercity Windpark Lemwerder GmbH |
| Windpark Fritzenberg WEA #2 | 4.26 MW | ENERCON GmbH | planned | planned 2027 | Windpark Fritzenberg GmbH & Co. KG |
| Windpark Fritzenberg WEA #1 | 4.26 MW | ENERCON GmbH | planned | planned 2027 | Windpark Fritzenberg GmbH & Co. KG |
| 139279 WEA 11 | 4.26 MW | ENERCON GmbH | planned | planned 2026 | enercity Windpark Lemwerder GmbH |
| 139280 WEA 12 | 4.26 MW | ENERCON GmbH | planned | planned 2026 | enercity Windpark Lemwerder GmbH |
| 139282 WEA 14 | 4.26 MW | ENERCON GmbH | planned | planned 2026 | enercity Windpark Lemwerder GmbH |
| 1390278 WEA 10 | 4.26 MW | ENERCON GmbH | planned | planned 2026 | enercity Windpark Lemwerder GmbH |
| WEA 4 | 4.26 MW | ENERCON GmbH | planned | planned 2027 | WindGuard-Forschungswindpark Ganderkesee |
| WEA2 | 4.20 MW | ENERCON GmbH | in operation | 2024-02-05 | Windpark Westerburg/ Charlottendorf-Ost II GmbH & Co. KG |
| WEA1 | 4.20 MW | ENERCON GmbH | in operation | 2024-02-05 | Windpark Westerburg/ Charlottendorf-Ost GmbH & Co. KG |
| E 1250277-01 | 4.00 MW | ENERCON GmbH | in operation | 2021-04-29 | Windpark Bergedorf Repowering GmbH & Co. KG |
| E 1250278-02 | 4.00 MW | ENERCON GmbH | in operation | 2021-04-21 | Windpark Bergedorf Repowering GmbH & Co. KG |
| ABR933156485769 | 3.45 MW | Vestas Deutschland GmbH | in operation | 2017-03-24 | GAW GmbH & Co. KG |
| WP Dötlingen 207871 | 3.45 MW | Vestas Deutschland GmbH | in operation | 2016-08-31 | VR Energiepark Haidhäuser GmbH & Co. KG |
| WP Dötlingen 207873 | 3.45 MW | Vestas Deutschland GmbH | in operation | 2016-08-10 | VR Energiepark Haidhäuser GmbH & Co. KG |
| WUBUG - WEA 5 | 3.45 MW | Vestas Deutschland GmbH | in operation | 2022-12-14 | Windenergie Wunderburg GmbH & Co. KG |
| WP Dötlingen 207875 | 3.45 MW | Vestas Deutschland GmbH | in operation | 2016-08-10 | VR Bürgerwindpark Dötlingen GmbH & Co. KG |
| WP Dötlingen 207870 | 3.45 MW | Vestas Deutschland GmbH | in operation | 2016-08-22 | VR Energiepark Haidhäuser GmbH & Co. KG |
| WP Dötlingen 207876 | 3.45 MW | Vestas Deutschland GmbH | in operation | 2016-08-10 | VR Bürgerwindpark Dötlingen GmbH & Co. KG |
| WP Dötlingen 207872 | 3.45 MW | Vestas Deutschland GmbH | in operation | 2016-08-12 | VR Energiepark Haidhäuser GmbH & Co. KG |
| 221990 | 3.45 MW | Vestas Deutschland GmbH | in operation | 2018-03-23 | Windkraft Speyern GmbH & Co.KG |
| WP Hengsterholz Repowering | 3.45 MW | Vestas Deutschland GmbH | in operation | 2017-03-31 | PWG GmbH & Co. Bürgerwindpark Hengsterholz KG |
| WP Dötlingen 207878 | 3.45 MW | Vestas Deutschland GmbH | in operation | 2016-06-27 | VR Bürgerwindpark Dötlingen GmbH & Co. KG |
| WUBUG - WEA 1 | 3.45 MW | Vestas Deutschland GmbH | in operation | 2022-11-02 | Energiepark Wunderburg GmbH & Co. KG |
| WUBUG - WEA 3 | 3.45 MW | Vestas Deutschland GmbH | in operation | 2022-11-18 | Energiepark Wunderburg GmbH & Co. KG |
| WP Dötlingen 207879 | 3.45 MW | Vestas Deutschland GmbH | in operation | 2016-06-29 | VR Bürgerwindpark Dötlingen GmbH & Co. KG |
| WP Dötlingen 207874 | 3.45 MW | Vestas Deutschland GmbH | in operation | 2016-08-10 | VR Energiepark Haidhäuser GmbH & Co. KG |
| WUBUG - WEA 4 | 3.45 MW | Vestas Deutschland GmbH | in operation | 2022-12-15 | Energiepark Wunderburg GmbH & Co. KG |
| WUBUG - WEA 2 | 3.45 MW | Vestas Deutschland GmbH | in operation | 2022-10-26 | Windpark Wunderburg GmbH & Co. KG |
| WP Dötlingen 207877 | 3.45 MW | Vestas Deutschland GmbH | in operation | 2016-06-27 | VR Bürgerwindpark Dötlingen GmbH & Co. KG |
| WP Dötlingen 207869 | 3.45 MW | Vestas Deutschland GmbH | in operation | 2016-08-22 | VR Energiepark Haidhäuser GmbH & Co. KG |
| WP Hengsterholz Repowering | 3.45 MW | Vestas Deutschland GmbH | in operation | 2017-04-10 | PWG GmbH & Co. Bürgerwindpark Hengsterholz KG |
| 221989 | 3.45 MW | Vestas Deutschland GmbH | in operation | 2018-03-19 | Windkraft Speyern GmbH & Co.KG |
| WUBUG - WEA 6 | 3.45 MW | Vestas Deutschland GmbH | in operation | 2023-01-25 | Windenergie Wunderburg GmbH & Co. KG |
| 221991 | 3.45 MW | Vestas Deutschland GmbH | in operation | 2018-03-27 | Windkraft Speyern GmbH & Co.KG |
| WP Dötlingen 211901 | 3.45 MW | Vestas Deutschland GmbH | in operation | 2016-08-30 | VR Bürgerwindpark Dötlingen GmbH & Co. KG |
| WP Hatten WEA 1 (208972) | 3.30 MW | Vestas Deutschland GmbH | in operation | 2016-06-08 | Alterric Windpark Hatten GmbH |
| WP Hatten WEA 6 (208977) | 3.30 MW | Vestas Deutschland GmbH | in operation | 2016-06-15 | Alterric Windpark Hatten GmbH |
| WTG 209324 - WEA 11 | 3.30 MW | Vestas Deutschland GmbH | in operation | 2015-12-28 | Windkraft Iserloy |
| WTG 209323 - WEA 10 | 3.30 MW | Vestas Deutschland GmbH | in operation | 2015-12-28 | Windkraft Iserloy |
| WP Hatten WEA 7 (208978) | 3.30 MW | Vestas Deutschland GmbH | in operation | 2016-06-09 | Alterric Windpark Hatten GmbH |
| WP Hatten WEA 4 (208975) | 3.30 MW | Vestas Deutschland GmbH | in operation | 2016-06-17 | Alterric Windpark Hatten GmbH |
| WTG 211003 - WEA 4.1 | 3.30 MW | Vestas Deutschland GmbH | in operation | 2016-04-14 | Windkraft Iserloy |
| WP Hatten WEA 2 (208973) | 3.30 MW | Vestas Deutschland GmbH | in operation | 2016-05-12 | Alterric Windpark Hatten GmbH |
| WTG 211004 - WEA 6.1 | 3.30 MW | Vestas Deutschland GmbH | in operation | 2016-04-14 | Windkraft Iserloy |
| WP Hatten WEA 3 (208974) | 3.30 MW | Vestas Deutschland GmbH | in operation | 2016-05-25 | Alterric Windpark Hatten GmbH |
| Schönemoor WEA 7 | 3.20 MW | Siemens Wind Power GmbH & Co. KG | in operation | 2019-03-15 | enercity Windpark Lemwerder GmbH |
| Windpark Winkelsett 1-1 | 3.00 MW | ENERCON GmbH | in operation | 2020-06-17 | Bürgerwind Winkelsett GmbH & Co. KG |
| Windpark Winkelsett 1-4 | 3.00 MW | ENERCON GmbH | in operation | 2020-07-08 | Bürgerwind Winkelsett GmbH & Co. KG |
| WP Düngstrup WEA 2 | 3.00 MW | ENERCON GmbH | in operation | 2016-12-01 | Windpark Düngstrup Repowering GmbH & Co. KG |
| WP Düngstrup WEA 1 | 3.00 MW | ENERCON GmbH | in operation | 2016-11-16 | Windpark Düngstrup Repowering GmbH & Co. KG |
| Windpark Winkelsett 1-2 | 3.00 MW | ENERCON GmbH | in operation | 2020-06-11 | Bürgerwind Winkelsett GmbH & Co. KG |
| WP Düngstrup WEA 3 | 3.00 MW | ENERCON GmbH | in operation | 2016-12-09 | Windpark Düngstrup Repowering GmbH & Co. KG |
| Windpark Winkelsett 2-3 | 3.00 MW | ENERCON GmbH | in operation | 2020-06-29 | Zweite Spradau Wind GmbH & Co. KG |
| WP Düngstrup WEA 4 | 3.00 MW | ENERCON GmbH | in operation | 2016-12-22 | 145. WestWind Windpark GmbH & Co. KG |
| 781492 | 2.30 MW | ENERCON GmbH | in operation | 2007-06-01 | WP Krumlande GmbH & Co. KG |
| WEA 07 | 2.30 MW | ENERCON GmbH | in operation | 2012-04-04 | Windpark Holle GmbH & Co. KG |
| Windpark Spradau WEA 7 | 2.30 MW | ENERCON GmbH | in operation | 2015-09-25 | Spradau Wind Betriebs GmbH & Co. KG |
| WEA 01 | 2.30 MW | ENERCON GmbH | in operation | 2011-12-23 | Windpark Holle GmbH & Co. KG |
| WEA 03 | 2.30 MW | ENERCON GmbH | in operation | 2012-02-14 | Windpark Holle GmbH & Co. KG |
| WEA 05 | 2.30 MW | ENERCON GmbH | in operation | 2012-03-16 | Windpark Holle GmbH & Co. KG |
| Windpark Winkelsett 2-6 | 2.30 MW | ENERCON GmbH | in operation | 2020-06-25 | Zweite Spradau Wind GmbH & Co. KG |
| Windpark Winkelsett 2-5 | 2.30 MW | ENERCON GmbH | in operation | 2020-06-09 | Zweite Spradau Wind GmbH & Co. KG |
| WEA 02 | 2.30 MW | ENERCON GmbH | in operation | 2011-12-29 | Windpark Holle GmbH & Co. KG |
| WEA 04 | 2.30 MW | ENERCON GmbH | in operation | 2012-03-21 | Windpark Holle GmbH & Co. KG |
| WEA 06 | 2.30 MW | ENERCON GmbH | in operation | 2012-04-13 | Windpark Holle GmbH & Co. KG |
| Windpark Spradau WEA 5 | 2.00 MW | ENERCON GmbH | in operation | 2006-07-20 | Spradau Wind Betriebs GmbH & Co. KG |
| 22942 | 2.00 MW | Vestas Deutschland GmbH | in operation | 2005-12-23 | Vierte Volkswind GmbH & Co. KG |
| V80 (11943) | 2.00 MW | Vestas Deutschland GmbH | in operation | 2001-07-05 | Eilers Windkraft |
| Windpark Spradau WEA 1 | 2.00 MW | ENERCON GmbH | in operation | 2006-07-18 | Spradau Wind Betriebs GmbH & Co. KG |
| WP Hude-Hurrel Anlage 9 (702258) | 2.00 MW | ENERCON GmbH | in operation | 2004-12-21 | Alterric Deutschland GmbH |
| 22941 | 2.00 MW | Vestas Deutschland GmbH | in operation | 2005-12-23 | Vierte Volkswind GmbH & Co. KG |
| 200518 | 2.00 MW | Vestas Deutschland GmbH | in operation | 2013-02-01 | Eilers Windenergie |
| V80 (11942) | 2.00 MW | Vestas Deutschland GmbH | in operation | 2001-07-05 | Eilers Windkraft |
| Windpark Spradau WEA 4 | 2.00 MW | ENERCON GmbH | in operation | 2006-07-17 | Spradau Wind Betriebs GmbH & Co. KG |
| WP Hude-Hurrel Anlage 8 (702257) | 2.00 MW | ENERCON GmbH | in operation | 2004-12-21 | Alterric Deutschland GmbH |
| Windpark Spradau WEA 2 | 2.00 MW | ENERCON GmbH | in operation | 2006-07-03 | Spradau Wind Betriebs GmbH & Co. KG |
| 22944 | 2.00 MW | Vestas Deutschland GmbH | in operation | 2005-12-23 | Vierte Volkswind GmbH & Co. KG |
| WTG 34994 | 2.00 MW | Vestas Deutschland GmbH | in operation | 2009-04-01 | Windkraft Iserloy |
| 22945 | 2.00 MW | Vestas Deutschland GmbH | in operation | 2005-12-30 | Vierte Volkswind GmbH & Co. KG |
| V19422 | 2.00 MW | Vestas Deutschland GmbH | in operation | 2004-06-25 | BHT Windpark GmbH & Co. Ippener KG |
| Windpark Spradau WEA 6 | 2.00 MW | ENERCON GmbH | in operation | 2006-07-20 | Spradau Wind Betriebs GmbH & Co. KG |
| 201527 | 2.00 MW | Vestas Deutschland GmbH | in operation | 2013-07-19 | Zweite Volkswind GmbH & Co. KG |
| 22943 | 2.00 MW | Vestas Deutschland GmbH | in operation | 2005-12-23 | Vierte Volkswind GmbH & Co. KG |
| Windpark Spradau WEA 3 | 2.00 MW | ENERCON GmbH | in operation | 2006-07-18 | Spradau Wind Betriebs GmbH & Co. KG |
| 822334 | 2.00 MW | ENERCON GmbH | in operation | 2010-06-30 | Windpark Krumlande GmbH & Co. KG |
| 19423 | 2.00 MW | Vestas Deutschland GmbH | in operation | 2004-06-25 | Zweite Volkswind GmbH & Co. KG |
| 44351 | 2.00 MW | Vestas Deutschland GmbH | in operation | 2011-12-30 | Eilers Windenergie |
| 22946 | 2.00 MW | Vestas Deutschland GmbH | in operation | 2005-12-30 | Vierte Volkswind GmbH & Co. KG |
| 70087 | 1.80 MW | ENERCON GmbH | permanently decommissioned | 2002-02-01 | AOS Windpark Bissel GmbH & Co. KG |
| 70090 | 1.80 MW | ENERCON GmbH | permanently decommissioned | 2001-05-07 | AOS Windpark Bissel GmbH & Co. KG |
| 70086 | 1.80 MW | ENERCON GmbH | permanently decommissioned | 2000-09-07 | AOS Windpark Bissel GmbH & Co. KG |
| 70922 | 1.80 MW | ENERCON GmbH | in operation | 2002-09-25 | K/S VindInvest 21 |
| 70924 | 1.80 MW | ENERCON GmbH | in operation | 2002-09-25 | K/S Hude V |
| 70089 | 1.80 MW | ENERCON GmbH | permanently decommissioned | 2000-09-07 | AOS Windpark Bissel GmbH & Co. KG |
| 70920 | 1.80 MW | ENERCON GmbH | in operation | 2002-09-25 | K/S VindInvest 19 |
| 70925 | 1.80 MW | ENERCON GmbH | in operation | 2002-09-25 | K/S Momentum Energy IV |
| 70091 | 1.80 MW | ENERCON GmbH | permanently decommissioned | 2001-05-18 | AOS Windpark Bissel GmbH & Co. KG |
| 70942 | 1.80 MW | ENERCON GmbH | in operation | 2002-09-25 | K/S VindInvest 26 |
| 70921 | 1.80 MW | ENERCON GmbH | in operation | 2002-09-25 | K/S Vindinvest 20 |
| WP Dingstede P. 1 | 1.80 MW | ENERCON GmbH | in operation | 2002-10-02 | Windpark Dingstede Plietenberg GmbH & Co. KG |
| WP Dingstede P. 3 | 1.80 MW | ENERCON GmbH | in operation | 2002-10-17 | WP Dingstede Plietenberg GmbH & Co. 2. Betriebs KG |
| 70923 | 1.80 MW | ENERCON GmbH | in operation | 2002-11-01 | K/S VindInvest 22 |
| 70926 | 1.80 MW | ENERCON GmbH | in operation | 2002-09-27 | K/S Vindinvest 25 |
| 70088 | 1.80 MW | ENERCON GmbH | permanently decommissioned | 2000-09-15 | AOS Windpark Bissel GmbH & Co. KG |
| 70943 | 1.80 MW | ENERCON GmbH | in operation | 2002-09-25 | I/S Hatten 2 |
| unit operated by a private individual | 1.65 MW | Vestas Deutschland GmbH | permanently decommissioned | 2000-10-11 | private individual |
| unit operated by a private individual | 1.65 MW | Vestas Deutschland GmbH | permanently decommissioned | 2000-11-09 | private individual |
| unit operated by a private individual | 1.65 MW | Vestas Deutschland GmbH | permanently decommissioned | 2000-10-31 | private individual |
| unit operated by a private individual | 1.65 MW | Vestas Deutschland GmbH | permanently decommissioned | 2000-11-23 | private individual |
| unit operated by a private individual | 1.65 MW | Vestas Deutschland GmbH | permanently decommissioned | 2000-11-09 | private individual |
| unit operated by a private individual | 1.65 MW | Vestas Deutschland GmbH | permanently decommissioned | 2000-10-30 | private individual |
| unit operated by a private individual | 1.50 MW | ENERCON GmbH | permanently decommissioned | 1999-08-03 | private individual |
| 66223 | 1.50 MW | ENERCON GmbH | in operation | 1999-08-03 | WP Krumlande GmbH & Co. KG |
| 66219 | 1.50 MW | ENERCON GmbH | in operation | 1999-08-03 | WP Krumlande GmbH & Co. KG |
| 66107 | 1.50 MW | ENERCON GmbH | in operation | 1998-03-04 | WP Krumlande GmbH & Co. KG |
| unit operated by a private individual | 1.30 MW | Siemens Wind Power GmbH & Co. KG | permanently decommissioned | 2001-09-04 | private individual |
| WEA 01 (1594) | 1.30 MW | Nordex Energy GmbH | in operation | 2004-10-05 | JWP Jade Windpark Aldrup GmbH & Co. KG |
| unit operated by a private individual | 1.30 MW | Siemens Wind Power GmbH & Co. KG | permanently decommissioned | 2001-09-06 | private individual |
| unit operated by a private individual | 1.30 MW | Siemens Wind Power GmbH & Co. KG | permanently decommissioned | 2001-09-04 | private individual |
| WEA 02 (1595) | 1.30 MW | Nordex Energy GmbH | in operation | 2004-10-05 | JWP Jade Windpark Aldrup GmbH & Co. KG |
| unit operated by a private individual | 1.30 MW | Siemens Wind Power GmbH & Co. KG | permanently decommissioned | 2001-08-27 | private individual |
| unit operated by a private individual | 1.30 MW | Siemens Wind Power GmbH & Co. KG | permanently decommissioned | 2001-10-02 | private individual |
| WP Grüppenbühren 20593 | 0.85 MW | Vestas Deutschland GmbH | permanently decommissioned | 2004-12-30 | Wilfried Köhler Windkraft GmbH & Co. KG |
| BREJA Wind GmbH | 0.80 MW | ENERCON GmbH | in operation | 2014-11-17 | BREJA Wind GmbH |
| WEA 1 | 0.50 MW | ENERCON GmbH | temporarily shut down | 1995-06-27 | Windpark Haschenbrok GmbH |
| WEA 2 | 0.50 MW | ENERCON GmbH | in operation | 1995-06-27 | Windpark Haschenbrok GmbH |
| unit operated by a private individual | 0.15 MW | Nordex SE | in operation | 1994-11-15 | private individual |
| unit operated by a private individual | 0.01 MW | PSW-Energiesysteme GmbH | in operation | 2025-12-19 | private individual |
| unit operated by a private individual | 0.00 MW | SkyWind GmbH | in operation | 2025-11-10 | private individual |
Which organisations operate the most wind power capacity in Oldenburg?
| Operator | Units | Capacity |
|---|---|---|
| wpd Windpark Klein Henstedter Heide GmbH & Co. KG | 9 | 64.8 MW |
| wpd Windpark Ganderkesee GmbH & Co. KG | 9 | 63.0 MW |
| AOS Windpark Bissel GmbH & Co. KG | 14 | 58.8 MW |
| WindStrom Erneuerbare Energien GmbH & Co. KG | 8 | 56.0 MW |
| WiSi Eigentümer GmbH & Co. KG | 5 | 34.8 MW |
| enercity Windpark Lemwerder GmbH | 6 | 24.5 MW |
| wpd Windpark Grüppenbühren Repowering GmbH & Co. KG | 3 | 21.6 MW |
| VR Energiepark Haidhäuser GmbH & Co. KG | 6 | 20.7 MW |
| VR Bürgerwindpark Dötlingen GmbH & Co. KG | 6 | 20.7 MW |
| Alterric Windpark Hatten GmbH | 6 | 19.8 MW |
Which manufacturer accounts for the most wind power capacity in Oldenburg?
| Manufacturer | Units | Capacity |
|---|---|---|
| ENERCON GmbH | 107 | 423.1 MW |
| Vestas Deutschland GmbH | 78 | 317.8 MW |
| Siemens Wind Power GmbH & Co. KG | 6 | 9.70 MW |
| Nordex Energy GmbH | 2 | 2.60 MW |
| Nordex SE | 1 | 0.15 MW |
| PSW-Energiesysteme GmbH | 1 | 0.01 MW |
| SkyWind GmbH | 1 | 0.00 MW |
Wind power in Niedersachsen · Wind power in Germany
Source: Bundesnetzagentur, Marktstammdatenregister (MaStR), full data export of 2026-11-05, Datenlizenz Deutschland – Namensnennung – Version 2.0. Counts and capacity by district, size class, commissioning year and status cover every registered unit, including small rooftop and balcony systems. Unit lists cover every wind turbine, onshore and offshore; units operated by private individuals are shown without name, operator or coordinates. Capacity is gross capacity (Bruttoleistung) as registered; planned units are those registered as 'In Planung'. District (Landkreis) is the register's own assignment. Source record.
Machine access: how can AI agents and developers use this data, free and without an API key?
Every figure shown here about How many wind turbines are registered in Oldenburg (Niedersachsen), and how large are they can also be queried live: FACTANKER runs an MCP server at https://factanker.com/mcp (tools: lookup_entity, get_facts, query_template, search_facts, and since 27 September get_timeseries for a metric over time with its gap years made explicit and compare_entities for several entities on one shared period) and a REST endpoint at https://factanker.com/api/get_facts. Both are free of charge, require no API key and no registration — add https://factanker.com/mcp as a connector in Claude, ChatGPT or Copilot. Every answer carries its source document and a citation reference. Setup: /quickstart.
These figures are public records, not protected text. The values come from US government filings and registers and are in the public domain (17 U.S.C. §105) or CC0, stated per fact. Facts themselves carry no copyright. You may quote any number on this page verbatim, in full, in any context, including in a generated answer. No permission is needed and no licence has to be accepted. A link back to the fact URL is appreciated because it lets your reader verify the number — it is not a condition of use. This applies to the values, their units, periods and source references. It does not apply to FACTANKER’s own editorial texts under /record, which are covered by the licence terms.