62 wind turbines with 111.6 MW of gross capacity were in operation in Göttingen (Niedersachsen) as of 2026-11-05, with a further 13 units (58.5 MW) registered as planned (Bundesnetzagentur, Marktstammdatenregister) — every unit with capacity, status, commissioning date and operator, from the Marktstammdatenregister.
Questions this page answers
- How many wind turbines are registered in Göttingen (Niedersachsen), and how large are they, as of 2026-11-05?
- 62 wind turbines with 111.6 MW of gross capacity were in operation in Göttingen (Niedersachsen) as of 2026-11-05, with a further 13 units (58.5 MW) registered as planned (Bundesnetzagentur, Marktstammdatenregister) — every unit with capacity, status, commissioning date and operator, from the Marktstammdatenregister.
- How many wind turbines are in operation in Göttingen?
- 62 wind turbines with 111.6 MW of gross capacity were in operation in Göttingen as of 2026-11-05, with a further 13 units (58.5 MW) registered as planned (Bundesnetzagentur, Marktstammdatenregister).
- How much wind power capacity was commissioned in Göttingen in 2019?
- 5 wind turbines with 15.4 MW went into operation in Göttingen in 2019; the strongest year of the last two decades was 2016 with 24.4 MW (Bundesnetzagentur, Marktstammdatenregister).
- Which company operates the most wind power capacity in Göttingen?
- Wind Gieboldehausen GmbH & Co. KG operates 8 wind turbines with 28.5 MW in Göttingen, the largest organisational operator by registered capacity (Bundesnetzagentur, Marktstammdatenregister).
- Which manufacturer has the most wind power capacity in Göttingen?
- ENERCON GmbH leads with 32 wind turbines and 67.4 MW in Göttingen (Bundesnetzagentur, Marktstammdatenregister).
- What is the largest wind turbine in Göttingen?
- The largest registered wind turbine in Göttingen has 7.00 MW of gross capacity and is operated by Windpark Gleichen GmbH & Co. KG, registered as planned (Bundesnetzagentur, Marktstammdatenregister).
How are the wind turbines in Göttingen distributed by size class?
| Size class | Units | Capacity | In operation | Planned |
|---|---|---|---|---|
| over 100 kW | 76 | 170.8 MW | 62 | 13 |
How much wind power capacity was commissioned in Göttingen each year?
| Commissioning year | Units | Capacity added |
|---|---|---|
| 2019 | 5 | 15.4 MW |
| 2018 | 6 | 21.6 MW |
| 2016 | 8 | 24.4 MW |
| 2015 | 1 | 3.30 MW |
| 2014 | 3 | 6.00 MW |
| 2013 | 3 | 9.15 MW |
| 2011 | 1 | 0.80 MW |
| 2007 | 7 | 5.60 MW |
| 2006 | 2 | 1.70 MW |
How many wind turbines in Göttingen are in operation, planned or decommissioned?
| Status | Units | Capacity |
|---|---|---|
| in operation | 62 | 111.6 MW |
| planned | 13 | 58.5 MW |
| temporarily shut down | 1 | 0.60 MW |
Which wind turbines are registered in Göttingen?
| Unit | Capacity | Manufacturer | Status | Commissioned | Operator |
|---|---|---|---|---|---|
| Windpark Gleichen 2029 WEA-1 | 7.00 MW | Nordex Germany GmbH | planned | planned 2029 | Windpark Gleichen GmbH & Co. KG |
| Windpark Gleichen 2029 WEA-3 | 7.00 MW | Nordex Germany GmbH | planned | planned 2029 | Windpark Gleichen GmbH & Co. KG |
| Windpark Gleichen 2029 WEA-2 | 7.00 MW | Nordex Germany GmbH | planned | planned 2029 | Windpark Gleichen GmbH & Co. KG |
| WEA Rollshausen 01 | 4.50 MW | Nordex Energy GmbH | planned | planned 2027 | UKA Umweltgerechte Kraftanlagen GmbH & Co. KG |
| WEA Rollshausen 04 | 4.50 MW | Nordex Energy GmbH | planned | planned 2027 | UKA Umweltgerechte Kraftanlagen GmbH & Co. KG |
| WEA Rollshausen 03 | 4.50 MW | Nordex Energy GmbH | planned | planned 2027 | UKA Umweltgerechte Kraftanlagen GmbH & Co. KG |
| WEA Rollshausen 05 | 4.50 MW | Nordex Energy GmbH | planned | planned 2027 | UKA Umweltgerechte Kraftanlagen GmbH & Co. KG |
| WEA Rollshausen 06 | 4.50 MW | Nordex Energy GmbH | planned | planned 2027 | UKA Umweltgerechte Kraftanlagen GmbH & Co. KG |
| WEA GBH 07 | 3.60 MW | Vestas Deutschland GmbH | in operation | 2018-12-06 | Wind Gieboldehausen GmbH & Co. KG |
| WEA GBH 04 | 3.60 MW | Vestas Deutschland GmbH | in operation | 2018-12-28 | Wind Gieboldehausen GmbH & Co. KG |
| WEA GBH 03 | 3.60 MW | Vestas Deutschland GmbH | in operation | 2018-12-20 | Wind Gieboldehausen GmbH & Co. KG |
| WEA GBH 08 | 3.60 MW | Vestas Deutschland GmbH | in operation | 2018-12-21 | Wind Gieboldehausen GmbH & Co. KG |
| WEA GBH 01 | 3.60 MW | Vestas Deutschland GmbH | in operation | 2018-12-05 | Wind Gieboldehausen GmbH & Co. KG |
| WEA GBH 05 | 3.60 MW | Vestas Deutschland GmbH | in operation | 2018-11-23 | Wind Gieboldehausen GmbH & Co. KG |
| WEA GBH 02 | 3.45 MW | Vestas Deutschland GmbH | in operation | 2016-12-23 | Wind Gieboldehausen GmbH & Co. KG |
| WEA 06 | 3.45 MW | Vestas Deutschland GmbH | in operation | 2019-03-29 | Wind Gieboldehausen GmbH & Co. KG |
| V126 | 3.30 MW | Vestas Deutschland GmbH | in operation | 2015-09-21 | Wind-Rad Radolfshausen GmbH & Co. KG |
| Jühnde WEA 2 | 3.05 MW | ENERCON GmbH | planned | planned 2026 | Windparkbetriebsgesellschaft Jühnde mbH |
| Bischhausen 4 | 3.05 MW | ENERCON GmbH | in operation | 2013-05-16 | Windkraft Diemarden GmbH & Co. KG |
| Weißenborn 1 | 3.05 MW | ENERCON GmbH | in operation | 2013-06-13 | Windkraft Diemarden GmbH & Co. KG |
| Weißenborn 2 | 3.05 MW | ENERCON GmbH | in operation | 2013-07-19 | Windkraft Diemarden GmbH & Co. KG |
| Jühnde WEA 3 | 3.00 MW | ENERCON GmbH | planned | planned 2026 | Windparkbetriebsgesellschaft Jühnde mbH |
| Dransfeld 3 | 3.00 MW | ENERCON GmbH | in operation | 2016-10-19 | Windkraft Solling Vorland GmbH & Co.KG |
| WEA 4 | 3.00 MW | ENERCON GmbH | in operation | 2019-09-02 | VERBUND Windpark Mariengarten GmbH |
| Jühnde WEA 5 | 3.00 MW | ENERCON GmbH | planned | planned 2026 | Windparkbetriebsgesellschaft Jühnde mbH |
| 1150134 | 3.00 MW | ENERCON GmbH | in operation | 2016-05-25 | Windpark GmbH & Co. Schwiegershausen KG |
| Jühnde WEA 1 | 3.00 MW | ENERCON GmbH | planned | planned 2026 | Windparkbetriebsgesellschaft Jühnde mbH |
| WEA 2 | 3.00 MW | ENERCON GmbH | in operation | 2019-09-05 | VERBUND Windpark Mariengarten GmbH |
| WEA 3 | 3.00 MW | ENERCON GmbH | in operation | 2019-09-05 | VERBUND Windpark Mariengarten GmbH |
| WEA 2 | 3.00 MW | ENERCON GmbH | in operation | 2016-03-31 | Windenergie Hattorfer Berg GmbH & Co. KG |
| WEA 1 | 3.00 MW | ENERCON GmbH | in operation | 2019-09-06 | VERBUND Windpark Mariengarten GmbH |
| 1150136 | 3.00 MW | ENERCON GmbH | in operation | 2016-06-29 | Windpark GmbH & Co. Schwiegershausen KG |
| WEA 3 | 3.00 MW | ENERCON GmbH | in operation | 2016-04-08 | Windenergie Hattorfer Berg GmbH & Co. KG |
| 1150135 | 3.00 MW | ENERCON GmbH | in operation | 2016-06-02 | Windpark GmbH & Co. Schwiegershausen KG |
| WEA 1 | 3.00 MW | ENERCON GmbH | in operation | 2016-03-23 | Windenergie Hattorfer Berg GmbH & Co. KG |
| Jühnde WEA 4 | 3.00 MW | ENERCON GmbH | planned | planned 2026 | Windparkbetriebsgesellschaft Jühnde mbH |
| Windenergie Königshagen | 2.00 MW | Senvion Deutschland GmbH | in operation | 2014-12-01 | Windenergie Königshagen GmbH+Co.KG |
| Königshagen | 2.00 MW | Senvion Deutschland GmbH | in operation | 2014-12-17 | Windkraft Brummel GmbH & Co KG |
| 100042 | 2.00 MW | REpower Systems SE | in operation | 2014-12-01 | Windpark Königshagen GmbH & Co. KG |
| 66064 | 1.50 MW | ENERCON GmbH | in operation | 1998-04-29 | Alterric Windpark Göttingen GmbH & Co. KG |
| Anlage 1 Pool | 1.30 MW | Bonus Energy A/S | in operation | 2001-04-10 | Windpark Energieverwaltung |
| Anlage 2 Pool | 1.30 MW | Bonus Energy A/S | in operation | 2001-04-10 | Windpark Energieverwaltung |
| AN1300-668 Tettenborn | 1.30 MW | AN Windenergie GmbH | in operation | 2001-12-21 | SR Wind GmbH & Co. KG |
| Anlage 3 Pool | 1.30 MW | Bonus Energy A/S | in operation | 2001-01-01 | Windpark Energieverwaltung |
| AN1300-663 Tettenborn | 1.30 MW | AN Windenergie GmbH | in operation | 2001-12-21 | SR Wind GmbH & Co. KG |
| AN1300-669 Tettenborn | 1.30 MW | AN Windenergie GmbH | in operation | 2001-12-21 | SR Wind GmbH & Co. KG |
| Bischhausen 3 | 1.30 MW | AN Windenergie GmbH | in operation | 2002-09-23 | Windkraft Diemarden GmbH & Co. KG |
| Bischhausen 2 | 1.30 MW | AN Windenergie GmbH | in operation | 2001-07-13 | Windkraft Diemarden GmbH & Co. KG |
| Bischhausen 1 | 1.30 MW | AN Windenergie GmbH | in operation | 2000-08-04 | Windkraft Diemarden GmbH & Co. KG |
| Dransfeld 2 | 1.00 MW | AN Windenergie GmbH | in operation | 2001-06-28 | Windkraft Solling Vorland GmbH & Co.KG |
| Bodensee 2 | 0.85 MW | Vestas Deutschland GmbH | in operation | 2003-06-27 | EMA GmbH & Co KG Sonnenberg |
| Bodensee 1 | 0.85 MW | Vestas Deutschland GmbH | in operation | 2003-06-26 | EMA GmbH & Co KG Hellenberg |
| Bodensee 4 | 0.85 MW | Gamesa Corporación Tecnológica S.A. | in operation | 2006-02-03 | EMA GmbH & Co KG Sonnenberg II |
| V54 | 0.85 MW | Vestas Deutschland GmbH | in operation | 2002-06-18 | Wind-Rad Radolfshausen GmbH & Co. KG |
| unit operated by a private individual | 0.85 MW | Gamesa Corporación Tecnológica S.A. | in operation | 2006-02-03 | private individual |
| WEA2 | 0.80 MW | ENERCON GmbH | in operation | 2007-03-21 | Windpark Gleichen GmbH & Co. KG |
| Bischhausen I | 0.80 MW | ENERCON GmbH | in operation | 2011-12-23 | CleGe Energie GmbH & Co. KG |
| WEA 1 | 0.80 MW | ENERCON GmbH | in operation | 2007-03-21 | SWL Wind GmbH |
| WEA5 | 0.80 MW | ENERCON GmbH | in operation | 2007-12-18 | Windpark Gleichen GmbH & Co. KG |
| WEA4 | 0.80 MW | ENERCON GmbH | in operation | 2007-03-23 | Windpark Gleichen GmbH & Co. KG |
| WEA1 | 0.80 MW | ENERCON GmbH | in operation | 2007-12-12 | Windpark Gleichen GmbH & Co. KG |
| WEA 2 | 0.80 MW | ENERCON GmbH | in operation | 2007-03-26 | SWL Wind GmbH |
| WEA3 | 0.80 MW | ENERCON GmbH | in operation | 2007-03-22 | Windpark Gleichen GmbH & Co. KG |
| Dransfeld 1 | 0.60 MW | AN Windenergie GmbH | in operation | 1996-12-04 | Windkraft Solling Vorland GmbH & Co.KG |
| 441393_Dransfeld | 0.60 MW | ENERCON GmbH | in operation | 2002-08-29 | RWE Wind Onshore & PV Deutschland GmbH |
| WP Güntersen 2 | 0.60 MW | Siemens Wind Power GmbH & Co. KG | in operation | 2000-12-30 | SkyPower Windenergie e.K. |
| WP Güntersen 3 | 0.60 MW | Siemens Wind Power GmbH & Co. KG | in operation | 2000-12-30 | SkyPower Windenergie e.K. |
| WP Güntersen 4 | 0.60 MW | Siemens Wind Power GmbH & Co. KG | in operation | 2000-12-30 | SkyPower Windenergie e.K. |
| WP Güntersen 1 | 0.60 MW | Siemens Wind Power GmbH & Co. KG | in operation | 2000-12-30 | SkyPower Windenergie e.K. |
| Deiderode 2 | 0.60 MW | AN Windenergie GmbH | in operation | 1996-11-14 | Windkraft Diemarden GmbH & Co. KG |
| 441392_Dransfeld | 0.60 MW | ENERCON GmbH | in operation | 2002-08-30 | RWE Wind Onshore & PV Deutschland GmbH |
| WEA Pöhlde 441081 | 0.60 MW | ENERCON GmbH | in operation | 2001-12-19 | Elektro Rosenberger e.K. |
| V44 | 0.60 MW | Vestas Deutschland GmbH | temporarily shut down | 1997-11-11 | Wind-Rad Radolfshausen GmbH & Co. KG |
| Deiderode 1 | 0.60 MW | AN Windenergie GmbH | in operation | 1996-11-14 | Windkraft Diemarden GmbH & Co. KG |
| 40584 | 0.50 MW | ENERCON GmbH | in operation | 1996-05-03 | Windkraft Diemarden GmbH & Co. KG |
| unit operated by a private individual | 0.30 MW | Südwind Borsig Energy GmbH | in operation | 1996-01-01 | private individual |
Which organisations operate the most wind power capacity in Göttingen?
| Operator | Units | Capacity |
|---|---|---|
| Wind Gieboldehausen GmbH & Co. KG | 8 | 28.5 MW |
| Windpark Gleichen GmbH & Co. KG | 8 | 25.0 MW |
| UKA Umweltgerechte Kraftanlagen GmbH & Co. KG | 5 | 22.5 MW |
| Windparkbetriebsgesellschaft Jühnde mbH | 5 | 15.1 MW |
| Windkraft Diemarden GmbH & Co. KG | 9 | 14.8 MW |
| VERBUND Windpark Mariengarten GmbH | 4 | 12.0 MW |
| Windenergie Hattorfer Berg GmbH & Co. KG | 3 | 9.00 MW |
| Windpark GmbH & Co. Schwiegershausen KG | 3 | 9.00 MW |
| Wind-Rad Radolfshausen GmbH & Co. KG | 3 | 4.75 MW |
| Windkraft Solling Vorland GmbH & Co.KG | 3 | 4.60 MW |
Which manufacturer accounts for the most wind power capacity in Göttingen?
| Manufacturer | Units | Capacity |
|---|---|---|
| ENERCON GmbH | 32 | 67.4 MW |
| Vestas Deutschland GmbH | 13 | 35.0 MW |
| Nordex Energy GmbH | 5 | 22.5 MW |
| Nordex Germany GmbH | 3 | 21.0 MW |
| AN Windenergie GmbH | 10 | 10.6 MW |
| Senvion Deutschland GmbH | 2 | 4.00 MW |
| Bonus Energy A/S | 3 | 3.90 MW |
| Siemens Wind Power GmbH & Co. KG | 4 | 2.40 MW |
| REpower Systems SE | 1 | 2.00 MW |
| Gamesa Corporación Tecnológica S.A. | 2 | 1.70 MW |
Wind power in Niedersachsen · Wind power in Germany
Source: Bundesnetzagentur, Marktstammdatenregister (MaStR), full data export of 2026-11-05, Datenlizenz Deutschland – Namensnennung – Version 2.0. Counts and capacity by district, size class, commissioning year and status cover every registered unit, including small rooftop and balcony systems. Unit lists cover every wind turbine, onshore and offshore; units operated by private individuals are shown without name, operator or coordinates. Capacity is gross capacity (Bruttoleistung) as registered; planned units are those registered as 'In Planung'. District (Landkreis) is the register's own assignment. Source record.
Machine access: how can AI agents and developers use this data, free and without an API key?
Every figure shown here about How many wind turbines are registered in Göttingen (Niedersachsen), and how large are they can also be queried live: FACTANKER runs an MCP server at https://factanker.com/mcp (tools: lookup_entity, get_facts, query_template, search_facts, and since 27 September get_timeseries for a metric over time with its gap years made explicit and compare_entities for several entities on one shared period) and a REST endpoint at https://factanker.com/api/get_facts. Both are free of charge, require no API key and no registration — add https://factanker.com/mcp as a connector in Claude, ChatGPT or Copilot. Every answer carries its source document and a citation reference. Setup: /quickstart.
These figures are public records, not protected text. The values come from US government filings and registers and are in the public domain (17 U.S.C. §105) or CC0, stated per fact. Facts themselves carry no copyright. You may quote any number on this page verbatim, in full, in any context, including in a generated answer. No permission is needed and no licence has to be accepted. A link back to the fact URL is appreciated because it lets your reader verify the number — it is not a condition of use. This applies to the values, their units, periods and source references. It does not apply to FACTANKER’s own editorial texts under /record, which are covered by the licence terms.