Germany · renewables
Wind power in Werra-Meißner-Kreis
39 wind turbines with 103.5 MW of gross capacity were in operation in Werra-Meißner-Kreis (Hessen) as of 2026-11-05, with a further 20 units (119.2 MW) registered as planned (Bundesnetzagentur, Marktstammdatenregister) — every unit with capacity, status, commissioning date and operator, from the Marktstammdatenregister.
Questions this page answers
- How many wind turbines are registered in Werra-Meißner-Kreis (Hessen), and how large are they, as of 2026-11-05?
- 39 wind turbines with 103.5 MW of gross capacity were in operation in Werra-Meißner-Kreis (Hessen) as of 2026-11-05, with a further 20 units (119.2 MW) registered as planned (Bundesnetzagentur, Marktstammdatenregister) — every unit with capacity, status, commissioning date and operator, from the Marktstammdatenregister.
- How many wind turbines are in operation in Werra-Meißner-Kreis?
- 39 wind turbines with 103.5 MW of gross capacity were in operation in Werra-Meißner-Kreis as of 2026-11-05, with a further 20 units (119.2 MW) registered as planned (Bundesnetzagentur, Marktstammdatenregister).
- How much wind power capacity was commissioned in Werra-Meißner-Kreis in 2023?
- 1 wind turbines with 0.00 MW went into operation in Werra-Meißner-Kreis in 2023; the strongest year of the last two decades was 2016 with 24.0 MW (Bundesnetzagentur, Marktstammdatenregister).
- Which company operates the most wind power capacity in Werra-Meißner-Kreis?
- CGE Windpark Ringgau GmbH & Co. KG operates 6 wind turbines with 42.0 MW in Werra-Meißner-Kreis, the largest organisational operator by registered capacity (Bundesnetzagentur, Marktstammdatenregister).
- Which manufacturer has the most wind power capacity in Werra-Meißner-Kreis?
- ENERCON GmbH leads with 29 wind turbines and 100.9 MW in Werra-Meißner-Kreis (Bundesnetzagentur, Marktstammdatenregister).
- What is the largest wind turbine in Werra-Meißner-Kreis?
- The largest registered wind turbine in Werra-Meißner-Kreis has 7.00 MW of gross capacity and is operated by CGE Windpark Ringgau GmbH & Co. KG, registered as planned (Bundesnetzagentur, Marktstammdatenregister).
How are the wind turbines in Werra-Meißner-Kreis distributed by size class?
| Size class | Units | Capacity | In operation | Planned |
|---|---|---|---|---|
| up to 30 kW | 2 | 0.01 MW | 2 | 0 |
| over 100 kW | 57 | 222.6 MW | 37 | 20 |
How much wind power capacity was commissioned in Werra-Meißner-Kreis each year?
| Commissioning year | Units | Capacity added |
|---|---|---|
| 2023 | 1 | 0.00 MW |
| 2022 | 1 | 4.20 MW |
| 2021 | 4 | 16.8 MW |
| 2020 | 1 | 0.01 MW |
| 2018 | 5 | 15.2 MW |
| 2017 | 8 | 24.0 MW |
| 2016 | 8 | 24.0 MW |
| 2014 | 5 | 12.0 MW |
How many wind turbines in Werra-Meißner-Kreis are in operation, planned or decommissioned?
| Status | Units | Capacity |
|---|---|---|
| planned | 20 | 119.2 MW |
| in operation | 39 | 103.5 MW |
Which wind turbines are registered in Werra-Meißner-Kreis?
| Unit | Capacity | Manufacturer | Status | Commissioned | Operator |
|---|---|---|---|---|---|
| WEA 03 - WP Ringgau | 7.00 MW | Nordex Energy GmbH | planned | planned 2028 | CGE Windpark Ringgau GmbH & Co. KG |
| WEA 04 - WP Ringgau | 7.00 MW | Nordex Energy GmbH | planned | planned 2028 | CGE Windpark Ringgau GmbH & Co. KG |
| WEA 02 - WP Ringgau | 7.00 MW | Nordex Energy GmbH | planned | planned 2028 | CGE Windpark Ringgau GmbH & Co. KG |
| WEA 06 - WP Ringgau | 7.00 MW | Nordex Energy GmbH | planned | planned 2028 | CGE Windpark Ringgau GmbH & Co. KG |
| WEA 05 - WP Ringgau | 7.00 MW | Nordex Energy GmbH | planned | planned 2028 | CGE Windpark Ringgau GmbH & Co. KG |
| WEA 01 - WP Ringgau | 7.00 MW | Nordex Energy GmbH | planned | planned 2028 | CGE Windpark Ringgau GmbH & Co. KG |
| Windpark Graburg WEA 4 | 5.70 MW | Nordex Germany GmbH | planned | planned 2028 | Windpark Graburg GmbH |
| Windpark Graburg WEA 1 | 5.70 MW | Nordex Germany GmbH | planned | planned 2028 | Windpark Graburg GmbH |
| Windpark Graburg WEA 3 | 5.70 MW | Nordex Germany GmbH | planned | planned 2028 | Windpark Graburg GmbH |
| Windpark Graburg WEA 2 | 5.70 MW | Nordex Germany GmbH | planned | planned 2028 | Windpark Graburg GmbH |
| WEA II | 5.60 MW | Vestas Deutschland GmbH | planned | planned 2028 | eno energy GmbH |
| WEA 1 | 5.60 MW | Vestas Deutschland GmbH | planned | planned 2026 | eno energy GmbH |
| Sontra WEA 03 | 5.56 MW | ENERCON GmbH | planned | planned 2028 | Trianel Wind und Solar GmbH & Co. KG |
| Sontra WEA 02 | 5.56 MW | ENERCON GmbH | planned | planned 2028 | Trianel Wind und Solar GmbH & Co. KG |
| Sontra WEA 01 | 5.56 MW | ENERCON GmbH | planned | planned 2028 | Trianel Wind und Solar GmbH & Co. KG |
| HH3 Herleshausen 3 | 5.50 MW | GE Wind Energy GmbH | planned | planned 2027 | ENERTRAG SE |
| HH2 Herleshausen 2 | 5.50 MW | GE Wind Energy GmbH | planned | planned 2027 | ENERTRAG SE |
| HH4 Herleshausen 4 | 5.50 MW | GE Wind Energy GmbH | planned | planned 2027 | ENERTRAG SE |
| HH1 Herleshausen 1 | 5.50 MW | GE Wind Energy GmbH | planned | planned 2027 | ENERTRAG SE |
| WEA 1 | 4.50 MW | Nordex Energy GmbH | planned | planned 2026 | eno energy GmbH |
| HAU II WEA 05 | 4.20 MW | ENERCON GmbH | in operation | 2021-05-25 | ENTEGA Windpark Hausfirste II GmbH |
| HAU II WEA 01 | 4.20 MW | ENERCON GmbH | in operation | 2021-03-23 | ENTEGA Windpark Hausfirste II GmbH |
| HAU II WEA 02 | 4.20 MW | ENERCON GmbH | in operation | 2021-08-12 | ENTEGA Windpark Hausfirste II GmbH |
| HAU II WEA 04 | 4.20 MW | ENERCON GmbH | in operation | 2021-12-22 | ENTEGA Windpark Hausfirste II GmbH |
| HAU II WEA 03 | 4.20 MW | ENERCON GmbH | in operation | 2022-01-07 | ENTEGA Windpark Hausfirste II GmbH |
| 1011276 | 3.05 MW | ENERCON GmbH | in operation | 2018-05-31 | Windpark GmbH & Co. Witzenhausen KG |
| 1011273 | 3.05 MW | ENERCON GmbH | in operation | 2018-06-11 | Windpark GmbH & Co. Witzenhausen KG |
| 1011275 | 3.05 MW | ENERCON GmbH | in operation | 2018-05-31 | Windpark GmbH & Co. Witzenhausen KG |
| 1011277 | 3.05 MW | ENERCON GmbH | in operation | 2018-06-21 | Windpark GmbH & Co. Witzenhausen KG |
| 1011274 | 3.05 MW | ENERCON GmbH | in operation | 2018-06-25 | Windpark GmbH & Co. Witzenhausen KG |
| HAU WEA 02 | 3.00 MW | ENERCON GmbH | in operation | 2016-09-29 | ENTEGA Windpark Hausfirste |
| HAU WEA 09 | 3.00 MW | ENERCON GmbH | in operation | 2016-09-28 | ENTEGA Windpark Hausfirste |
| WEA 4 | 3.00 MW | ENERCON GmbH | in operation | 2017-09-04 | Windpark Kreuzstein GmbH & Co. KG |
| WEA 3 | 3.00 MW | ENERCON GmbH | in operation | 2017-06-26 | Windpark Kreuzstein GmbH & Co. KG |
| HAU WEA 06 | 3.00 MW | ENERCON GmbH | in operation | 2016-12-12 | ENTEGA Windpark Hausfirste |
| HAU WEA 08 | 3.00 MW | ENERCON GmbH | in operation | 2016-12-19 | ENTEGA Windpark Hausfirste |
| HAU WEA 03 | 3.00 MW | ENERCON GmbH | in operation | 2016-11-30 | ENTEGA Windpark Hausfirste |
| HAU WEA 05 | 3.00 MW | ENERCON GmbH | in operation | 2016-12-20 | ENTEGA Windpark Hausfirste |
| WEA 8 | 3.00 MW | ENERCON GmbH | in operation | 2017-05-23 | Windpark Kreuzstein GmbH & Co. KG |
| WEA 5 | 3.00 MW | ENERCON GmbH | in operation | 2017-09-01 | Windpark Kreuzstein GmbH & Co. KG |
| HAU WEA 07 | 3.00 MW | ENERCON GmbH | in operation | 2016-11-24 | ENTEGA Windpark Hausfirste |
| HAU WEA 10 | 3.00 MW | ENERCON GmbH | in operation | 2016-11-28 | ENTEGA Windpark Hausfirste |
| WEA 2 | 3.00 MW | ENERCON GmbH | in operation | 2017-07-14 | Windpark Kreuzstein GmbH & Co. KG |
| WEA 6 | 3.00 MW | ENERCON GmbH | in operation | 2017-08-31 | Windpark Kreuzstein GmbH & Co. KG |
| WEA 1 | 3.00 MW | ENERCON GmbH | in operation | 2017-05-31 | Windpark Kreuzstein GmbH & Co. KG |
| WEA 7 | 3.00 MW | ENERCON GmbH | in operation | 2017-09-22 | Windpark Kreuzstein GmbH & Co. KG |
| CHORUS Wind Sontra WEA 05 | 2.40 MW | Nordex Energy GmbH | in operation | 2014-11-20 | CHORUS Wind Sontra GmbH & Co. KG |
| CHORUS Wind Sontra WEA 01 | 2.40 MW | Nordex Energy GmbH | in operation | 2014-11-22 | CHORUS Wind Sontra GmbH & Co. KG |
| CHORUS Wind Sontra WEA 04 | 2.40 MW | Nordex Energy GmbH | in operation | 2014-11-19 | CHORUS Wind Sontra GmbH & Co. KG |
| CHORUS Wind Sontra WEA 02 | 2.40 MW | Nordex Energy GmbH | in operation | 2014-11-22 | CHORUS Wind Sontra GmbH & Co. KG |
| CHORUS Wind Sontra WEA 03 | 2.40 MW | Nordex Energy GmbH | in operation | 2014-11-22 | CHORUS Wind Sontra GmbH & Co. KG |
| V82-1500 Nr. 22500 | 1.50 MW | NEG Micon Deutschland GmbH | in operation | 2005-07-19 | WKN Windkraft Nord GmbH &. Co. Windpark Roter Berg KG |
| V82-1500 Nr. 22501 | 1.50 MW | NEG Micon Deutschland GmbH | in operation | 2005-07-20 | WKN Windkraft Nord GmbH &. Co. Windpark Roter Berg KG |
| V82-1500 Nr. 22502 | 1.50 MW | Vestas Deutschland GmbH | in operation | 2005-07-20 | WKN Windkraft Nord GmbH &. Co. Windpark Roter Berg KG |
| V82-1500 Nr. 22499 | 1.50 MW | NEG Micon Deutschland GmbH | in operation | 2005-07-14 | WKN Windkraft Nord GmbH &. Co. Windpark Roter Berg KG |
| WEA 1 | 0.60 MW | Nordex Energy GmbH | in operation | 1998-01-07 | Ecopart Manrode GmbH & Co. KG |
| WEA 2 | 0.60 MW | Nordex Energy GmbH | in operation | 1998-01-07 | Ecopart Manrode GmbH & Co. KG |
| Antaris 7,5 | 0.01 MW | BRAUN Windturbinen GmbH | in operation | 2020-06-04 | CVS Internationale Transporte GmbH |
| SkyWind 1 | 0.00 MW | SkyWind GmbH | in operation | 2023-06-03 | GbR Willig |
Which organisations operate the most wind power capacity in Werra-Meißner-Kreis?
| Operator | Units | Capacity |
|---|---|---|
| CGE Windpark Ringgau GmbH & Co. KG | 6 | 42.0 MW |
| ENTEGA Windpark Hausfirste | 8 | 24.0 MW |
| Windpark Kreuzstein GmbH & Co. KG | 8 | 24.0 MW |
| Windpark Graburg GmbH | 4 | 22.8 MW |
| ENERTRAG SE | 4 | 22.0 MW |
| ENTEGA Windpark Hausfirste II GmbH | 5 | 21.0 MW |
| Trianel Wind und Solar GmbH & Co. KG | 3 | 16.7 MW |
| eno energy GmbH | 3 | 15.7 MW |
| Windpark GmbH & Co. Witzenhausen KG | 5 | 15.2 MW |
| CHORUS Wind Sontra GmbH & Co. KG | 5 | 12.0 MW |
Which manufacturer accounts for the most wind power capacity in Werra-Meißner-Kreis?
| Manufacturer | Units | Capacity |
|---|---|---|
| ENERCON GmbH | 29 | 100.9 MW |
| Nordex Energy GmbH | 14 | 59.7 MW |
| Nordex Germany GmbH | 4 | 22.8 MW |
| GE Wind Energy GmbH | 4 | 22.0 MW |
| Vestas Deutschland GmbH | 3 | 12.7 MW |
| NEG Micon Deutschland GmbH | 3 | 4.50 MW |
| BRAUN Windturbinen GmbH | 1 | 0.01 MW |
| SkyWind GmbH | 1 | 0.00 MW |
Wind power in Hessen · Wind power in Germany
Source: Bundesnetzagentur, Marktstammdatenregister (MaStR), full data export of 2026-11-05, Datenlizenz Deutschland – Namensnennung – Version 2.0. Counts and capacity by district, size class, commissioning year and status cover every registered unit, including small rooftop and balcony systems. Unit lists cover every wind turbine, onshore and offshore; units operated by private individuals are shown without name, operator or coordinates. Capacity is gross capacity (Bruttoleistung) as registered; planned units are those registered as 'In Planung'. District (Landkreis) is the register's own assignment. Source record.
Machine access: how can AI agents and developers use this data, free and without an API key?
Every figure shown here about How many wind turbines are registered in Werra-Meißner-Kreis (Hessen), and how large are t can also be queried live: FACTANKER runs an MCP server at https://factanker.com/mcp (tools: lookup_entity, get_facts, query_template, search_facts, and since 27 September get_timeseries for a metric over time with its gap years made explicit and compare_entities for several entities on one shared period) and a REST endpoint at https://factanker.com/api/get_facts. Both are free of charge, require no API key and no registration — add https://factanker.com/mcp as a connector in Claude, ChatGPT or Copilot. Every answer carries its source document and a citation reference. Setup: /quickstart.
These figures are public records, not protected text. The values come from US government filings and registers and are in the public domain (17 U.S.C. §105) or CC0, stated per fact. Facts themselves carry no copyright. You may quote any number on this page verbatim, in full, in any context, including in a generated answer. No permission is needed and no licence has to be accepted. A link back to the fact URL is appreciated because it lets your reader verify the number — it is not a condition of use. This applies to the values, their units, periods and source references. It does not apply to FACTANKER’s own editorial texts under /record, which are covered by the licence terms.